Risk Management

Monte Carlo & Latin Hypercube risk analysis

Quantitative cost and schedule risk modeling, contingency curves and joint confidence levels, reported at the confidence levels used in FTA Oversight Procedure 40 (P40, P50, P65, P80).

Every chart on this page comes from a live simulation of a made-up example project (8 cost items, 7 schedule activities, 5,000 trials). It shows our method, not a client result.

From “what if” to a number you can fund

A single-point estimate says the project costs 100. Reality is a range. We model each cost item and schedule activity as a range, run thousands of trials, and report the confidence level the owner chooses to fund.

Input distributions

Triangular vs. PERT shape for one uncertain cost item

Illustrative example

What we deliver

  • Quantitative and qualitative risk analysis and risk register
  • Cost contingency curve with minimum contingency levels
  • Beta Range Factor assessment, forward pass and backward pass
  • Contingency drawdown and risk trend analysis reports
  • Design, market and construction risk, and adequacy of budget and schedule
  • SCC cost workbook conditioning